Halstead Cluster Maintenance

July 16, 2019  8:00am – 5:00pm
Halstead
Download Calander Event

UPDATE: July 16, 2019  12:34pm

As of 12:30, maintenance tasks on the Halstead cluster have been completed successfully, and it has been returned to normal service.


ORIGINAL: June 17, 2019  8:30am

The Halstead cluster will be unavailable beginning Tuesday, July 16th, 2019 at 8:00am for a scheduled maintenance. The cluster will return to full production by Tuesday, July 16th, 2019 at 5:00pm.

During this time, Halstead will have minor operating system security patches and upgrades applied.

Any PBS jobs which request a walltime which would take them past Tuesday, July 16th, 2019 at 8:00am will not start and will remain in the queue until after the maintenance is completed.

Originally posted: June 17, 2019  8:30am